New Zealand Cycle Trail Funding Process
Last updated:
October 2009
The funding process for Phase Two of the New Zealand Cycle Trail project was announced by the Ministry of Tourism on 15 October 2009.
The process to apply for funding will occur in three stages.
Read this guide to the funding process for full details of how to apply.
Read through answers to questions about the Cycleway Funding Process.
The purpose of stage one is to satisfy the Funding Committee that the proposal is sufficiently aligned with the objectives and assessment criteria of the Fund to progress to stage two (feasibility study).
The minimum requirements of a feasibility study are set out in the Feasibility Study Guidance Notes.
Stage three is the submission of a business case and a funding request for the detailed design and construction of the cycleway.
Timeframes for the funding process are expected to be as follows:
- 18 December 2009: Closing date for applicants to submit concept proposals to the Ministry.
- 1 February 2010: Applicants notified of whether the proposal will proceed to stage two (feasibility study).
- 31 May 2010: Feasibility studies completed.
- 30 June 2010: Proposals to proceed to stage three (business case) notified
- 30 September 2010: Business cases completed.
- October 2010: Approved cycleways confirmed for detailed design and construction funding (subject to any conditions of funding).